Written by Raja Zaman, Head of Business Performance at GMPA LLC. Raja spent over 10 years managing stores for Tesco and Iceland and has 10 years of experience in accounting and tax.
Construction companies in Qatar often run out of cash on profitable projects. The reason is timing. You pay labour, subcontractors and suppliers every month, but you are paid only when a certificate is approved and settled, and part of every payment is held back as retention. A project cash flow forecast shows that timing gap before it becomes a crisis.
Start from the contract, not the profit forecast
Your project budget tells you how much the job should make. It does not tell you when the cash moves. Before you forecast anything, pull these terms from the contract:
- Any advance payment, and how it is recovered from later certificates
- How often you can submit valuations or interim payment applications
- The period for certifying and then paying each certificate
- The retention percentage and when it is released, often part at completion and part after the defects liability period
- Bond and guarantee requirements, and their cost
Step 1: Map the payment cycle
For each month of the project, estimate the value of work you will complete. Then work out when that becomes cash: the date you submit the application, the date it is certified, and the date the money actually reaches your bank. In 2026, the gap between doing the work and being paid on Qatar projects is still often two to four months, and longer on some government and main contractor projects.
Step 2: Deduct retention and advance recovery
From each certified amount, deduct retention and any advance payment recovery. Track retention in its own column. It is money you have earned but cannot use, and it should never be counted as available cash.
Step 3: Forecast your payments
- Site labour through the Wage Protection System, monthly
- Subcontractors, on the terms you have agreed with each one
- Materials and suppliers, including any deposits
- Plant and equipment hire
- Site overheads, insurance and bond charges
Step 4: Find the peak funding need
Subtract payments from receipts month by month and keep a running total. The lowest point of that running total is the most cash the project will need from the business before it starts paying for itself. That figure, not the profit margin, decides whether you can afford to take the job.
| Month | Work done | Cash received | Cash paid out | Running total |
|---|---|---|---|---|
| 1 | 400,000 | 0 | 350,000 | −350,000 |
| 2 | 600,000 | 0 | 520,000 | −870,000 |
| 3 | 700,000 | 360,000 | 600,000 | −1,110,000 |
| 4 | 500,000 | 540,000 | 430,000 | −1,000,000 |
| 5 | 300,000 | 630,000 | 260,000 | −630,000 |
In this illustration (QAR), the project needs over QAR 1.1 million of working capital at its peak in month 3, even though it is profitable overall. Receipts are shown net of 10% retention.
Step 5: Roll projects up into a company forecast
Most contractors run several projects at once. Add each project’s forecast together with head office costs to get a company-wide view, then keep a 13 week cash flow forecast for the near term. Update both monthly as certificates are approved.
Managing working capital in construction
- Chase certificate approvals as hard as you chase invoices
- Agree subcontractor and supplier terms that line up with your payment cycle
- Keep retentions in a separate receivable and track release dates
- Use WIP reporting to spot over-billed and under-billed jobs early
- Forecast the peak funding need before you bid for a new contract
Where we can help
We provide bookkeeping, management accounts and CFO support for contractors in Qatar, including project cash flow forecasts, WIP reporting and margin by project. If you are not sure where cash is going, our Business Performance Diagnostic is a good place to start.
Frequently asked questions
How do you forecast construction project cash flow?
Start from the contract payment terms. Map when each certificate will be submitted, approved and paid, deduct retention and advance recovery, then set that against when you pay labour, subcontractors and suppliers.
Why do profitable construction projects run out of cash?
Because costs are paid monthly while income arrives only after certificates are approved and paid, and part of each payment is held as retention. The project can need significant working capital before it pays for itself.
How should retention be treated in a cash flow forecast?
As money earned but not available. Track it separately with its expected release dates and never count it as usable cash.
Want a cash flow forecast for your projects?
If you want to talk it through, message Raja on WhatsApp and we will arrange a short call.